Research

year 1996 
author Hanil Jeong 
Keyword Batch Splitting, Improving Schedule, Job Shop Scheduling, Before-Arrival Family Setup Time, Branch and Bound 
Abstract The job shop scheduling problem has been a major target for many researchers. However, most of the past studies assumed that a job consists of only a single part. With this assumption, the master production schedule and MRP output must be modified when production requirement from MRP( Material Requirement Planning )for a planning period exceeds the capacity of production system.

In addition to that, a real factory is full of unexpectedness and dynamics. Due to such dynamic nature of shop floor, the requirements for production volume and due date can not easily be satisfied under the assumption that a job consists of a single part. In many cases of real manufacturing environment, however, a job does not consist of a single part but a set of parts of same type, so-called a batch. We can alleviate the problems mentioned above by considering characteristics of batch. That is to say, if we allow each part which constitute a batch to be processed independently, then we can obtain an improved schedule because we can fill up the idle times of machines with jobs of smaller processing time. However, then, the size of the scheduling problem would become too large to be solved in practical time limit, and the clerical work will also increase to handle the increased number of production orders. And so, there may be an optimum batch size considering trade-off between better solution and tractability.

We propose an improved scheduling algorithm when a job consists of a batch. For this algorithm, we try to minimize makespan or maximum lateness for job shop scheduling problem considering before-arrival family setup time, transportation time, release date and due date. Our scheduling algorithm can be divided into two parts. The first part selects a batch to be splitted and splits it into smaller batches. The second part solves the new job shop scheduling problem with smaller batches. The batch splitting algorithm selects a batch to be splitted based on information of lateness and idle time, and then its size is determined by batch splitting strategy. The proposed job shop scheduling algorithm contains a new branch and bound algorithm to minimize makespan for single machine sequencing problem considering before-arrival family setup time, release date and delivery time. This algorithm starts with obtaining a single machine sequencing problem using the characteristic values of operation from disjunctive graph which represents job shop scheduling problem. Final solution is obtained by applying proposed single machine sequencing algorithm iteratively. The proposed new branch and bound algorithm for single machine sequencing problem consists of five modules, they are branching, determining precedence, modifying characteristic values of operations, generating heuristic solution and calculating lower bound modules.

Experimental results show that the proposed single machine sequencing algorithm finds an optimal solution within small time limit. The proposed job shop scheduling algorithm shows better performance than tabu search, simulated annealing and genetic algorithm, and error rates compared to optimal solution is low. The batch splitting algorithm shows that only a few split can improve schedule considerably, and we can handle dynamic events more elegantly by this algorithm. 
c PhD 

Downlaod :

번호 c year 제목 author
26 PhD  1995  Design Support System for the Conceptual Design of Manufacturing Databases [13] Kitae Shin 
25 PhD  1991  An Integrated Decision Support System for FMS Planning and Control Problems [11] Seongyoung Jang 
24 PhD  1994  A Study on Design of a Cooperative- Distributed Shop Floor Control System for Computer Integrated Manufacturing [19] Namkyu Park 
» PhD  1996  An Improved Scheduling Heuristic Based on Batch Splitting Method for The Job Shop Scheduling Problem [4] Hanil Jeong 
22 PhD  1996  A Design Support System for the Process Design of Computer Integrated Manufacturing [2] Chankwon Park 
21 PhD  1997  A Study on the Integration of Process Planning and Scheduling [3] Kidong Kim 
20 PhD  1997  Computer-Aided Synthesis of the Execution Controllers for Workcells in Computer Integrated Manufacturing Systems [18] Sangkyun Kim 
19 PhD  1997  A Study on FMS Design Justification Considering Part Type Selection and Performance Evaluation Hosub Shin 
18 PhD  1997  A Study on the Integration of Loading and Scheduling in Flexible Manufacturing Systems [21] Sangbok Woo 
17 PhD  1999  A Study on Job Shop Scheduling Problems considering Production Capacity Adjustment [16] Daeyoung Chung 
16 PhD  1999  A Study on the Manufacturing System State Based Scheduler using Neural Network and Simulator [20] Kitae Kim 
15 PhD  2002  Flexible Job Shop Scheduling with Multi-level Job Structures [16] Yangja Jang 
14 PhD  2003  Process Modeling and Performance Analysis Methodology toward Optimal Design of Manufacturing Systems [30] Kichang Lee 
13 PhD  2004  Ontology Development for e-Business Integration [26] Tai-Woo Chang 
12 PhD  2005  A Study on the Integration of Quality Designing and Process Control in Steel Industry [15] Jonghan Kim 
11 PhD  2005  Performance Analysis and Network Design of Supply Chain for Strategic Decision Making [14] Eoksu Sim 
10 PhD  2005  Development of an algorithm for multi-plant production plans in a supply chain [50] Sungwon Jung 
9 PhD  2008  A study on integrated production planning and strategic framework in supply chain [15] Haejoong Kim 
8 PhD  2009  A Study for Business Process Improvement Using Real-time Information of Unbalanced Work [19] Jaehyun Kong 
7 PhD  2010  Framework for Integrative SRM System and Collaboration Scorecard [26] Jongkyoung Park 
6 PhD  2007  A Study on MRP Process Improvement in a Grid Enabled APS [2] file Hyoung-Gon Lee 
5 PhD  2010  Enhancing Flexibility and Responsiveness in Sales Order Management [54] Mokmin Park 
4 PhD  2013  Price of Simplicity under Congestion: On the Revenue and Pricing Schemes in the Telecommunication Industry [58] file Dongmyung Lee 
3 PhD  2013  A study on production scheduling problems considering differential electricity pricing and distributed generations Jun Young Moon 
2 PhD  2014  Multi-level job scheduling in a flexible discrete-part production environment Hong Bum Na 
1 PhD  2014  A study on integrative decision-making system for reconfigurable manufacturing cells Jin Wu Seo