year 1996 
author Hanil Jeong 
Keyword Batch Splitting, Improving Schedule, Job Shop Scheduling, Before-Arrival Family Setup Time, Branch and Bound 
Abstract The job shop scheduling problem has been a major target for many researchers. However, most of the past studies assumed that a job consists of only a single part. With this assumption, the master production schedule and MRP output must be modified when production requirement from MRP( Material Requirement Planning )for a planning period exceeds the capacity of production system.

In addition to that, a real factory is full of unexpectedness and dynamics. Due to such dynamic nature of shop floor, the requirements for production volume and due date can not easily be satisfied under the assumption that a job consists of a single part. In many cases of real manufacturing environment, however, a job does not consist of a single part but a set of parts of same type, so-called a batch. We can alleviate the problems mentioned above by considering characteristics of batch. That is to say, if we allow each part which constitute a batch to be processed independently, then we can obtain an improved schedule because we can fill up the idle times of machines with jobs of smaller processing time. However, then, the size of the scheduling problem would become too large to be solved in practical time limit, and the clerical work will also increase to handle the increased number of production orders. And so, there may be an optimum batch size considering trade-off between better solution and tractability.

We propose an improved scheduling algorithm when a job consists of a batch. For this algorithm, we try to minimize makespan or maximum lateness for job shop scheduling problem considering before-arrival family setup time, transportation time, release date and due date. Our scheduling algorithm can be divided into two parts. The first part selects a batch to be splitted and splits it into smaller batches. The second part solves the new job shop scheduling problem with smaller batches. The batch splitting algorithm selects a batch to be splitted based on information of lateness and idle time, and then its size is determined by batch splitting strategy. The proposed job shop scheduling algorithm contains a new branch and bound algorithm to minimize makespan for single machine sequencing problem considering before-arrival family setup time, release date and delivery time. This algorithm starts with obtaining a single machine sequencing problem using the characteristic values of operation from disjunctive graph which represents job shop scheduling problem. Final solution is obtained by applying proposed single machine sequencing algorithm iteratively. The proposed new branch and bound algorithm for single machine sequencing problem consists of five modules, they are branching, determining precedence, modifying characteristic values of operations, generating heuristic solution and calculating lower bound modules.

Experimental results show that the proposed single machine sequencing algorithm finds an optimal solution within small time limit. The proposed job shop scheduling algorithm shows better performance than tabu search, simulated annealing and genetic algorithm, and error rates compared to optimal solution is low. The batch splitting algorithm shows that only a few split can improve schedule considerably, and we can handle dynamic events more elegantly by this algorithm. 
c PhD 

Downlaod :

번호 c year 제목 author
111 MS  1988  A Simulation Study on Operating Rules of FMS Considering Tool Change Byunghoon Yoo 
110 MS  1988  Development of a Classification and Coding System through Fuzzy Sets Approach [1] Namkyu Park 
109 MS  1988  A Study on The Machine-Part Group Formation for FMS Planning and Operation Jaeyoon Kim 
108 MS  1989  A Study on the Computer and Database Location of Distributed Computer Systems in FMS [1] Kilsup Yang 
107 MS  1989  An FMS Planning Algorithm Considering Tool Magazine Capacity and Alternative Routings [6] Chankwon Park 
106 MS  1989  A Mathematical Decision Making Model for Real-Time Scheduling of an FMS Jonghan Kim 
105 MS  1990  A Fuzzy Linguistic Approach to the Part Selection Problem in FMS [1] Yoosuk Hong 
104 MS  1990  A Study on Data Allocation Problems for Distributed Database Design [2] Kitae Shin 
103 MS  1991  A Study on Scheduling Problem of Hierarchically Structured Products in FMS [1] Hanil Jeong 
102 MS  1991  A Study on Performance Evaluation of Production Plan for FMS Using Queueing Network [1] Sangbok Woo 
101 MS  1991  A Study on the Layered Architecture for the Control of FMS Cells Hosub Shin 
100 MS  1991  A Study on Image Processing and CAD - Vision System Interface of Manufactured Parts [1] Kidong Kim 
99 PhD  1991  An Integrated Decision Support System for FMS Planning and Control Problems [11] Seongyoung Jang 
98 MS  1992  A Study on Production Planning Problems in a Flexible Machining and Assembly System [1] Sukang Lee 
97 MS  1992  Event-Driven On-Line Operational Control of Flexible Manufacturing Systems Jonghun Park 
96 MS  1992  A Decision Support System for A Machine Specifications in Design of An FMS [6] Youngkwan Ko 
95 MS  1993  A Study on the Computer-Aided Process Planning for Rotational Parts Considering Machine Status [1] Sungbum Chun 
94 MS  1993  A Comparative Analysis of Production Control Policies under Production Uncertainty [5] Janghan Lee 
93 MS  1993  A Study on Effects of Order Release Policies to Performance of Manufacturing Systems Choonghwan Ahn 
92 MS  1993  A Study on the FMS Shop Floor Control by Bidding among Autonomous Objects Jangsuk Moon 
91 MS  1993  A Supervisory Control Approach to Rapid Implementation of Low-Level Control Software for FMC [1] Sangkyun Kim 
90 MS  1994  A Study on Distributed Shop Floor Control of Flexible Manufacturing Systems [4] Daeyoung Chung 
89 MS  1994  A Study on Development of a Knowledge Based Scheduler and Knowledge Acquisition through Simulation [1] Kitae Kim 
88 PhD  1994  A Study on Design of a Cooperative- Distributed Shop Floor Control System for Computer Integrated Manufacturing [19] Namkyu Park 
87 MS  1994  A Finitely Recursive Processes Approach to Modeling and Control of an FMC Jaeheuk Choi 
86 PhD  1995  Design Support System for the Conceptual Design of Manufacturing Databases [13] Kitae Shin 
85 MS  1995  A Study on knowledge Acquisition for Simulation-based Scheduling Expert System [1] Soohyun Lee 
84 MS  1995  A study on intelligent dispatching strategy in Automated Manufacturing Systems [5] Seongwoo Lee 
83 MS  1995  An Object-Oriented Framework for the Implementation of Distributed Shop Floor Control in FMS [2] Kyungsuk Lee 
82 MS  1995  A study on Real-Time Collection of Shop Floor Data Using Speech Recognition [2] Namjoo Kim 
81 MS  1995  A Study on the Group Scheduling Problem with Sequence-dependent Set-up Times in a Multi-stage Cellular Manufacturing Systems Jaesoo Shim 
80 MS  1996  A Study on the Generation and DB Construction of Modular BOM [1] Yonggu Ji 
» PhD  1996  An Improved Scheduling Heuristic Based on Batch Splitting Method for The Job Shop Scheduling Problem [4] Hanil Jeong 
78 PhD  1996  A Design Support System for the Process Design of Computer Integrated Manufacturing [2] Chankwon Park 
77 PhD  1997  A Study on the Integration of Process Planning and Scheduling [3] Kidong Kim 
76 MS  1997  A Scheduling Algorithm Considering Subcontractor and Machine Setup Cost in MRP Environment [1] Kichang Lee 
75 MS  1997  A Study on FMS Scheduling Problems Based on Priority Functions Generated by Genetic Programming ChangUk Kim 
74 MS  1997  A New Approach to Master Production Scheduling in the MRP environment [1] Sangdo Choi 
73 PhD  1997  Computer-Aided Synthesis of the Execution Controllers for Workcells in Computer Integrated Manufacturing Systems [18] Sangkyun Kim 
72 PhD  1997  A Study on FMS Design Justification Considering Part Type Selection and Performance Evaluation Hosub Shin 
71 PhD  1997  A Study on the Integration of Loading and Scheduling in Flexible Manufacturing Systems [21] Sangbok Woo 
70 MS  1998  A study on an efficient real-time deadlock-free control algorithm by using graph-theoretic approach [27] Jungwoon Yoo 
69 MS  1998  A Study on UML representation of CIM-OSA and availability of analysis and design pattern in CIM-OSA [1] Seungoh Han 
68 MS  1998  Design of Integrated BOM Management System supporting Multiple Views Keumseok Kang 
67 PhD  1999  A Study on Job Shop Scheduling Problems considering Production Capacity Adjustment [16] Daeyoung Chung 
66 PhD  1999  A Study on the Manufacturing System State Based Scheduler using Neural Network and Simulator [20] Kitae Kim 
65 MS  1999  An Evaluation of Workload Limited Order Release Strategies considering Planning Stage in a Jop Shop Byeongdae Choi 
64 MS  1999  A Study on the Development of Event-driven MRP Components Considering Capacity Constraints [1] Seunghyun Yoon 
63 MS  1999  A Study on the Implementation of the Speech Recognition System for the Real-Time Decision Support of Manufacturing Cells [18] Eoksu Sim 
62 MS  2000  A Study on Work Measurement Using Image Processing [8]