Research

year 1999 
author Daeyoung Chung 
Keyword job shop scheduling, production planning, operation subcontract, overtime, decomposition 
Abstract Reliable and timely delivery is an important factor determining the competitive strength of a manufacturing company. In some environment, keeping due date is considered as a constraint whose violation is not permitted. However, a production plan and promised due dates usually cannot be accomplished owing to diverse reasons including insufficient production capacity and unexpected events. To cope with such problems, loads are modified using alternative routing, subcontracting, overtime work, etc. Capacity adjustments are usually considered in production planning, but the plan cannot correctly reflect the limited capacities of production resources. So the intervention of human planner is inevitable to rectify the plan, but the performance of the resulting plan is usually inferior with respect to costs because the human planner does not have proper decision support tools. To make a cost efficient plan, the capacity adjustment should be considered at scheduling level.

This paper deals with a job shop scheduling problem considering operation subcontract and overtime work. The problem has more decision variables and complex constraints than the pure job shop scheduling problem, which traditionally has been regarded as one of the most difficult combinatorial optimization problems. Due to the characteristic of the problem, decomposition and synthesis method is proposed to get the solution. First, the solution method starts with a traditional job shop scheduling problem with an objective of minimizing the violation of due date constraints. Second, the subcontract operations are repeatedly selected to reduce the remaining violation while minimizing the costs. At each iteration step, the overtime plans are modified to minimize the total cost of adjusting production capacities. Incidentally, the proposed solution methodology could also be utilized to solve an independent sub-problems of this type.

Next, a job shop scheduling problem with an objective of minimizing maximum lateness is addressed, and an optimization method and a heuristic algorithm are developed. The optimization method transforms the problem into a series of constraint satisfaction problems (CSP), and solves the CSP until an optimal solution is found. In this research, a new variable ordering / value ordering method and an improved dichotomous search method are introduced. Being implemented with an efficient constraint propagation technique, the suggested method shows superior performance than the other existing methods. The heuristic algorithm aims to find good solutions by improving the schedules obtained by widely used dispatching rules. The algorithm is designed to incrementally reduce the maximum lateness by repeatedly re-sequencing the jobs on bottleneck machines with Carlier´s algorithm. Perceiving that the jobs spend much waiting time owing to poor sequencing decisions, the algorithm is designed to select the bottleneck machine by relaxing the capacity constraint. The suggested method was shown to improve the quality of the solution more than the critical pair-wise exchange method in a very short time.

Next, a job shop scheduling problem considering operation subcontract is defined, and its solution method is suggested. The problem is decomposed into two sub-problems that are much related with each other, and so we would better not to use a sequential approach. Reflecting the relationship of the sub-problems, a solution method that deals with the sub-problems in an integrated manner is developed. In short, re-sequencing of the jobs and the selection of subcontracting operations are repeatedly conducted on bottleneck machines. To select the subcontracting operations with minimum cost, a branch and bound algorithm was developed. However, during the actual application of the algorithm, it was discovered that the maximum lateness cannot be decreased sometimes. To clear the cause of the stall and to make a way out, an algorithm that transforms the problem into a maximum flow problem is also developed. Through experiments, it is shown that the suggested solution method outperforms the conventional method and the sequential approaches.

Overtime scheduling is a difficult problem that must consider the time availability of production resources. An implicit representation method that relaxes the time availability constraint and a time-based decomposition method are used to circumvent the difficulties. As a result, the original problem can be solved by successive determination of overtime production quantity in each period. To determine the overtime quantity of a period, a linear programming model is used. The LP model considers the constraints occurred by the release time of a job and the operations planned to be subcontract.

The results of this study can be utilized to support the decision making of a human planner by generating a plan with minimum cost. Also this study may be considered as one of the first attempts to integrate the production planning problems and production scheduling problems. 
c PhD 

Download :

번호 c year 제목 author
61 MS  2004  A Study on business process model for extended and integrated supply chain planning : Focused on negotiation [5] Yuncheol Kang 
60 MS  2004  A Design on Cost-Estimation Support System for Injection Mold Using AI Method [12] Gunhee Kim 
59 MS  2004  A study on due-date assignment method in wafer fabrication facility producing multiple product types [3] Jaewon Park 
58 MS  2005  A Study on RFID application in Reverse Supply Chain [3] Dongjoon Lim 
57 MS  2005  Development of Reference Model and Strategic Road Map for the Implementation of a Reverse Supply Chain [183] Chihoon Lim 
56 MS  2005  A Study on Developing of Position collecting Vision system Using Marker [1] Jiyoon Park 
55 MS  2005  A Study on Product Development Methodology in Reverse Supply Chain [77] Joon Kim 
54 MS  2006  A Study on the Application of Group Technology for Naval Ship Design And Manufacturing: Relating to Platform Family Architecture [17] Gwangjae Park 
53 MS  2006  A Framework for the ubiquitous MES using RFID and Web services Technology [25] Manchul Han 
52 MS  2006  A Study on the Assessment Method of Installation and Operation Cost in a Reverse Supply Chain [2] file Hyunjong Jeong 
51 MS  2007  A Study on the Valuation of a Supply Chain Considering Management Efficiency and Environmental Effect [53] Jiyoun Kim 
50 MS  2008  An Study abou the Application and Effect of RFID Technology in the Activity Collecting Information to Improvement of Manufacturing Process [10] Sungho Jo 
49 MS  2009  A Fuzzy-AHP based Decision making Model for ground operations [37] Youngkyun Lee 
48 MS  2009  A Study on Integrated Risk Management in Supply Chain - Focusing on High-tech Electronic Industry [52] file Kanghyun Kim 
47 MS  2009  A Study on Mine Artillery Hit Using Simulation [3] Youngho Chung 
46 MS  2009  A Study on the Economic Feasibility of Automated Identification Technology on the ELV Management Process [25] file Kiheon Nam 
45 MS  2007  A Study on Project Risk Management based on Earned Value Management [25] file Hyunil Noh 
44 MS  2007  A Study on BOM for Enhancing Efficiency of Reverse Supply Chain [14] Jinseon Yoo 
43 MS  2007  A Study on Utility Value and Fairness of Information Sharing in Supply Chain [18] file Myongran Oh 
42 MS  2007  A Simulation Study on the Impact of RFID Technology on the Supply Chain Counting Process [13] file Jangwon Cho 
41 MS  2008  A study on supplier's performance measurements for a supply chain on a new product environment [1] Jungsub Lee 
40 MS  2008  Integration of RFID and Web Service Technology in Manufacturing Systems [20] file Gunnam Ong 
39 MS  2011  A Study on RMC Scheduling using Simulation [19] Jeongho Park 
38 MS  2011  Intelligent service during middle-of-life phase of a product: Illustration of framework and its evaluation model [3] Soyeon Yoon 
37 MS  2011  A Study on Real Time Progress Monitoring Methodology and Effects based on RTLS in Project Shop [27] Kyounghwi Tae 
36 MS  2011  A System Study to Improve the Infromation Flow of Unused Drug Recovery After Customer Point Reach in Pharmaceutical Reverse Logistics [2] Youngjee Hong 
35 MS  2011  The Development of a Strategic Model of Freight Transportation between Korea and Europe [525] Louis Coulet 
34 MS  2012  The study on target allocation model using simulation for counter-fire execution [22] Jeonghun Kim 
33 MS  2012  Flight and Maintenance Planning of Miliary Aircraft considering Preventive Maintenance Period [13] Jun-Ho Park 
32 MS  2012  Load Leveling in Project Scheduling Using Partial Adjustment and Diffusional Relaxation Method [12] SungHoon KIM 
31 MS  2012  Load Leveling in Project Scheduling Considering Work-in-Process Inventory [18] Sungjin Lee 
30 MS  2013  Design of an inspection system for reducing quality deterioration under VMI supply chain management system [16] Jaebong Lee 
29 MS  2013  Developing integrated key performance indicators and measurement scheme for MES [19] file Gyusun Hwang 
28 MS  2014  A study on operational models for electric vehicle battery switch stations in smart grid environment Dong Hyun Kim 
27 MS  2014  A hybrid algorithm for production scheduling under Make-to-Order environment : a case study from the transformer industry Sung Bum Jun 
26 PhD  1995  Design Support System for the Conceptual Design of Manufacturing Databases [13] Kitae Shin 
25 PhD  1991  An Integrated Decision Support System for FMS Planning and Control Problems [11] Seongyoung Jang 
24 PhD  1994  A Study on Design of a Cooperative- Distributed Shop Floor Control System for Computer Integrated Manufacturing [19] Namkyu Park 
23 PhD  1996  An Improved Scheduling Heuristic Based on Batch Splitting Method for The Job Shop Scheduling Problem [4] Hanil Jeong 
22 PhD  1996  A Design Support System for the Process Design of Computer Integrated Manufacturing [2] Chankwon Park 
21 PhD  1997  A Study on the Integration of Process Planning and Scheduling [3] Kidong Kim 
20 PhD  1997  Computer-Aided Synthesis of the Execution Controllers for Workcells in Computer Integrated Manufacturing Systems [18] Sangkyun Kim 
19 PhD  1997  A Study on FMS Design Justification Considering Part Type Selection and Performance Evaluation Hosub Shin 
18 PhD  1997  A Study on the Integration of Loading and Scheduling in Flexible Manufacturing Systems [21] Sangbok Woo 
» PhD  1999  A Study on Job Shop Scheduling Problems considering Production Capacity Adjustment [16] Daeyoung Chung 
16 PhD  1999  A Study on the Manufacturing System State Based Scheduler using Neural Network and Simulator [20] Kitae Kim 
15 PhD  2002  Flexible Job Shop Scheduling with Multi-level Job Structures [16] Yangja Jang 
14 PhD  2003  Process Modeling and Performance Analysis Methodology toward Optimal Design of Manufacturing Systems [30] Kichang Lee 
13 PhD  2004  Ontology Development for e-Business Integration [26] Tai-Woo Chang 
12 PhD  2005  A Study on the Integration of Quality Designing and Process Control in Steel Industry [15] Jonghan Kim